[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388326":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388326,172,1,"单选题","某项目包含 A、 B、 C、 D、 E、 F、G七个活动，各活动的历时估算和活动间的逻辑关系如下表所示，活动C的总浮动时间是1天，该项目工期是（ ）天",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","13",false,{"key":16,"text":17,"correct":14},"B","14",{"key":19,"text":20,"correct":21},"C","15",true,{"key":23,"text":24,"correct":14},"D","16","由图可知，关键路径ADFG，工期2+6+4+3=15C的总浮动时间=8-7=1",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]