[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388323":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388323,172,1,"单选题","以下关于工程项目范围确认与质量控制的表述中，正确的是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","范围确认是有关工作结果的可接受问题，质量控制是有关工作结果是否满足质量需求的问题",true,{"key":16,"text":17,"correct":18},"B","范围确认与质量控制相同",false,{"key":20,"text":21,"correct":18},"C","质量控制通常是在范围确认之前进行，这2个过程是串行执行的",{"key":23,"text":24,"correct":18},"D","范围确认的输入包含项目分解结构字典，质量控制输入不包含项目分解结构字典","A和D均可范围确认是有关工作结果的可接受问题，质量控制是有关工作结果是否满足质量需求的问题。两者有区别，质量控制和范围确认是并行关系，同属于监控过程组。确切的说结构字典是创建WBS的输出，所以选A最好。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]