[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388322":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388322,172,1,"单选题","（ ）属于控制范围的活动。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","与客户仔细讨论项目范围说明书，并请客户签字",false,{"key":16,"text":17,"correct":18},"B","当客户提出新的需求时，说服用户放弃新的需求",true,{"key":20,"text":21,"correct":14},"C","确认项目范围是否覆盖了需要完成的产品或服务进行的所有活动",{"key":23,"text":24,"correct":14},"D","确认每项工作是否有明确的质量最标准","排除法，ACD选项属于范围确认的内容。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]