[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388314":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388314,172,1,"单选题","不能作为检验WBS是否定义完全，项目的所有任务是否都被完全分解的依据是（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","是否明确定义了每个任务的开始和结束",false,{"key":16,"text":17,"correct":14},"B","是否每个任务都有一个可交付的成果",{"key":19,"text":20,"correct":14},"C","是否容易估算成本",{"key":22,"text":23,"correct":24},"D","是否明确了变更申请",true,"是否明确了变更申请与检验WBS是否定义完全，项目的所有任务是否都被完全分解无关。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]