[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388312":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388312,172,1,"单选题","关于WBS的描述，不正确的是：（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","WBS必须且只能包括100%的工作",false,{"key":16,"text":17,"correct":18},"B","WBS的元素必须指定一个或多个负责人",true,{"key":20,"text":21,"correct":14},"C","WBS应该由全体项目成员、用户和项目干系人一致确认",{"key":23,"text":24,"correct":14},"D","分包出去的工作也应纳入WBS中","WBS中的元素必须有人负责，而且只由一人负责，实际上可能由多个人参与。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]