[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388310":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388310,172,1,"单选题","某拟建项目财务净现金流量如下表所示，该项目的静态投资回收期是（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","5.4",false,{"key":16,"text":17,"correct":14},"B","5.6",{"key":19,"text":20,"correct":21},"C","7.4",true,{"key":23,"text":24,"correct":14},"D","7.6","静态投资回收期，不考虑时间价值，计算到什么时候为正值。-1200+（-1000）+200+300+500+500++500+200=0也就是说，第八年现金流为200的时候完成回收期，200\u002F500=0.4，第八年只需要0.4年即可，7+0.4=7.4",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]