[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388300":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388300,172,1,"单选题","以下各项中，（ ）不是整体变更控制的输入。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","己批准的纠正措施",true,{"key":16,"text":17,"correct":18},"B","变更请求",false,{"key":20,"text":21,"correct":18},"C","实际的绩效数据",{"key":23,"text":24,"correct":18},"D","己批准的项目管理计划","整体变更控制的依据是：1、项目管理计划（已经批准的）2、工作绩效报告3、变更请求4、事业环境因素5、组织过程资产已批准的纠正措施不是整体变更控制的依据，变更请求可能包括纠正措施、预防措施和缺陷补救。纠正错误是还未批准的。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]