[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388295":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388295,172,1,"单选题","项目管理计划的内容不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","沟通管理计划",false,{"key":16,"text":17,"correct":18},"B","选择的生命周期模型",true,{"key":20,"text":21,"correct":14},"C","资源日历",{"key":23,"text":24,"correct":14},"D","成本基准","一个项目管理计划一般包括项目范围管理计划、进度管理计划、成本管理计划、质量管理计划、过程改进计划、人员配备管理计划、沟通管理计划、风险管理计划、采购管理计划等分计划。项目管理计划详略均可，可由一个或多个部分计划，以及其他事项组成，其他部分可以包括：里程碑清单、资源日历、进度基准、成本基准、质量基准、风险登记册等。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]