[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388280":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388280,172,1,"单选题","投标文件存在对招标文件响应的非实质性的微小偏差，则该投标文件应（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不予淘汰，但需在订立合同前予以澄清",false,{"key":16,"text":17,"correct":18},"B","不予淘汰，但需在评估结束前予以澄清",true,{"key":20,"text":21,"correct":14},"C","不予淘汰，允许投标人重新投标",{"key":23,"text":24,"correct":14},"D","予以淘汰","评标委员会可以要求投标人对投标文件中含义不明确的内容作必要的澄清或者说明，但是澄清或者说明不得超出投标文件的范围或者改变投标文件的实质性内容。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]