[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388277":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388277,172,1,"单选题","在信息系统项目可行性研究报告中，项目实施进度计划和项目招标方案一般属于（ ）研究的内容",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","政策可行性",false,{"key":16,"text":17,"correct":14},"B","经济可行性",{"key":19,"text":20,"correct":14},"C","市场可行性",{"key":22,"text":23,"correct":24},"D","技术可行性",true,"排除法即可。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]