[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388255":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388255,172,1,"单选题","系统集成项目完成了需求分析阶段的工作并开发了原型系统，承建方应组织本方项目经理、建设方代表和相关干系人完成（ ）工作。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","代码走查",false,{"key":16,"text":17,"correct":14},"B","桌面检查",{"key":19,"text":20,"correct":14},"C","同行评审",{"key":22,"text":23,"correct":24},"D","阶段评审",true,"系统集成项目完成了需求分析阶段的工作并开发了原型系统，因此应完成“D.阶段评审”",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]