[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388057":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388057,171,1,"单选题","某软件项目的活动图如下图所示，其中顶点表示项目里程碑，连接顶点的边表示包含的活动，边上的数字表示活动的持续天数，则完成该项目的最少时间为（ ）天。活动EH和IJ的松弛时间分别为（ ）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3和3",false,{"key":16,"text":17,"correct":14},"B","3和6",{"key":19,"text":20,"correct":21},"C","5和3",true,{"key":23,"text":24,"correct":14},"D","5和6","在网络图中的某些活动可以并行地进行，所以完成工程的最少时间是从开始顶点到结束顶点的最长路径长度，从开始顶点到结束顶点的最长（工作时间之和最大）路径为关键路径，关键路径上的活动为关键活动。 本题关键路径为：A-B-D-G-I-K-L，共22天。 EH的松弛时间是22-（2+3+2+4+6）=5天。 IJ的松弛时间是22-（2+5+2+6+3+1）=3天。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)系统架构设计师","职业资格",0]