[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388055":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388055,171,1,"单选题","某软件项目的活动图如下图所示，其中顶点表示项目里程碑，连接顶点的边表示包含的活动，边上的数字表示活动的持续天数，则完成该项目的最少时间为（ ）天。活动EH和IJ的松弛时间分别为（ ）天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","17",false,{"key":16,"text":17,"correct":14},"B","19",{"key":19,"text":20,"correct":14},"C","20",{"key":22,"text":23,"correct":24},"D","22",true,"",{"id":6,"name":27,"category":28,"favorite":29},"(高级)系统架构设计师","职业资格",0]