[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388054":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388054,171,1,"单选题","某软件项目的活动图如下图所示，其中顶点表示项目里程碑，连接顶点的边表示包含的活动，边上的数字表示活动的持续时间(天)，则完成该项目的最少时间为（ ）天。活动BD和HK最早可以从第（ ）天开始。(活动A B、AE和AC最早从第1天开始)",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","17",false,{"key":16,"text":17,"correct":14},"B","18",{"key":19,"text":20,"correct":14},"C","19",{"key":22,"text":23,"correct":24},"D","20",true,"由于在一个项目中时间最长的活动序列，决定着项目最短工期。而时间最长的是ABDIJL，需要时间20，所以答案是D。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)系统架构设计师","职业资格",0]