[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388053":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388053,171,1,"单选题","某软件项目的活动图如下图所示，其中顶点表示项目里程碑，链接顶点的边表示包含的活动，边上的数字表示活动的持续时间（天）。完成该项目的最少时间为（ ）天。由于某种原因，现在需要同一个开发人员完成BC和B D，则完成该项目的最少时间为（请作答此空）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","11",false,{"key":16,"text":17,"correct":14},"B","18",{"key":19,"text":20,"correct":21},"C","20",true,{"key":23,"text":24,"correct":14},"D","21","BC持续时间3天，BD持续时间2天，由一人完成，则可以把先完成BD，再完成BC，则BC持续时间作为5天，则关键路径为ABCEFJ， 20天。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)系统架构设计师","职业资格",0]