[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-387618":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},387618,170,1,"单选题","某公司签署的服务器运维项目的核算表如下所示，该项目已结项，其投资回报 率为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","14.49%",false,{"key":16,"text":17,"correct":14},"B","16.95%",{"key":19,"text":20,"correct":21},"C","17.65%",true,{"key":23,"text":24,"correct":14},"D","22.2%","项目投资回报率=项目利润\u002F项目投资总额X100%，本题：项目收入200万元，项目成本=120+26+9.6+4.4+2.5+7.5=170万元，项目利润=200-167=30万元，投资回报率=30\u002F170=17.65%",{"id":6,"name":27,"category":28,"favorite":29},"(高级)系统规划与管理师","职业资格",0]