[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-387534":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},387534,169,1,"单选题","某工程项目包括8个作业A～H。各作业的紧前作业、所需天数、所需人数见下表： 项目的成本管理中，（ ）将总的成本估算分配到各项活动和工作包上，来建立一个成本的基线。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","成本估算",false,{"key":16,"text":17,"correct":18},"B","成本预算",true,{"key":20,"text":21,"correct":14},"C","成本跟踪",{"key":23,"text":24,"correct":14},"D","成本控制","成本管理过程包括：成本估算、成本预算与成本控制。其中成本预算的含义是将总的成本估算分配到各项活动和工作包上，来建立一个成本的基线。而成本估算是对完成项目活动所需资金进行近似的估算。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)系统分析师","职业资格",0]