[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-387504":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},387504,169,1,"单选题","某项目有 A~H 八个作业,各作业所需时间(单位:周)以及紧前作业如下表 该项目的工期为( )周。如果作业C 拖延3 周完成,则该项目的工期(请作答此空)",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","不变",false,{"key":16,"text":17,"correct":14},"B","拖延1周",{"key":19,"text":20,"correct":21},"C","拖延2周",true,{"key":23,"text":24,"correct":14},"D","拖延3周","画出网络图可知，ADFH为关键路径，工期为1+5+6+1=13。若C拖延3周，关键路径变为ACEH，工期为1+6+7+1=15，总体拖延2周。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)系统分析师","职业资格",0]