[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-387296":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},387296,169,1,"单选题","某工程包括 A、 B、 C、 D、 E、F 六个作业，分别需要 5、7、3、4、15、12 天。A 必须在 C、D 开始之前完成， B、D 必须在 E 开始之前完成，C 必须在 F 开始之前完成，F 不能在 B、D 完成之前开始。若作业 E 缩短 4 天，则整个工期可以缩短（ ）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","21",false,{"key":16,"text":17,"correct":14},"B","22",{"key":19,"text":20,"correct":21},"C","24",true,{"key":23,"text":24,"correct":14},"D","46","关键路径为ADE，工期24天。 E 缩短 4 天后，关键路径变为ADF，工期21天。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)系统分析师","职业资格",0]