[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386611":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},386611,168,1,"单选题","某系统集成企业迫于经营的压力，承接了一个极具技术风险的项目，该项目的项目经理为此：调用了公司最有能力的人力资源，组织项目组核心团队成员培训，与该项目技术领域最强的研究团队签订项目技术分包协议，从项目风险管理的角度来看，该项目经理采取了正向风险的应对策略，并采取了（ ）风险应对措施。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","转移、分享、提高",false,{"key":16,"text":17,"correct":14},"B","开拓、接受、提高",{"key":19,"text":20,"correct":14},"C","减轻、分享、规避",{"key":22,"text":23,"correct":24},"D","开拓、分享、强大",true,"此风险属于积极风险应对（正向风险）。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)网络规划设计师","职业资格",0]