[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386593":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},386593,168,1,"单选题","某系统集成企业迫于经营的压力，承接了一个极具技术风险的项目，该项目的项目经理为此：调用了公司最有能力的人力资源，组织项目组核心团队成员培训，与该项目技术领域最强的研究团队签订项目技术分包协议，从项目风险管理的角度来看，该项目经理采取了（ ）的应对策略。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","应急分享",false,{"key":16,"text":17,"correct":18},"B","正向风险",true,{"key":20,"text":21,"correct":14},"C","转移风险",{"key":23,"text":24,"correct":14},"D","负面风险","此风险属于积极风险应对（正向风险）。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)网络规划设计师","职业资格",0]