[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386535":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},386535,168,1,"单选题","在项目进度管理中，常用（）来安排工作顺序。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进度曲线法",false,{"key":16,"text":17,"correct":18},"B","网络图法",true,{"key":20,"text":21,"correct":14},"C","直方图法",{"key":23,"text":24,"correct":14},"D","相关图法","网络图法是一种编制大型工程进度计划的有效方法。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)网络规划设计师","职业资格",0]