[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386528":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},386528,168,1,"单选题","在项目的每一个阶段结束时，审查项目完成情况与可交付成果是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","根据项目基线确定完成项目所需的资源数量",false,{"key":16,"text":17,"correct":14},"B","根据已完成的工作量调整时间安排与成本基线",{"key":19,"text":20,"correct":21},"C","决定项目是否应进入下一阶段",true,{"key":23,"text":24,"correct":14},"D","接受客户对所交付项目的验收","本题考查项目阶段性管理的基本知识。 在项目的每个阶段结束时，都要对项目完成情况与可交付成果进行审查，以确定项目是否应进入下一阶段。每个阶段的成果可看成是一个里程碑。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)网络规划设计师","职业资格",0]