[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386335":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},386335,167,1,"单选题","进度、费用、质量是工程项目管理的三个重要目标，当SPI",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","进度超前，费用节余",false,{"key":16,"text":17,"correct":14},"B","进度滞后，费用节余",{"key":19,"text":20,"correct":14},"C","进度超前，费用超支",{"key":22,"text":23,"correct":24},"D","进度滞后，费用超支",true,"进度业绩指标SPI=EV\u002FPV（SPI>1.0 表示进度超前，SPI 1.0 表示费用节余，CPI\u003C1.0 表示费用超支）。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统监理师","职业资格",0]