[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386330":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},386330,167,1,"单选题","某项目由并行的3个模块 A、B和C组成，其中活动A需要3人5天时间完成。活动B需要6人7天时间完成。活动C需要4人2天时间完成，为了保证项目在最短时间内完成。则最少应该为项目配置（ ）人。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","7人",false,{"key":16,"text":17,"correct":14},"B","9人",{"key":19,"text":20,"correct":21},"C","10人",true,{"key":23,"text":24,"correct":14},"D","11人","首先题目要求的是“在最短时间内完成”，同时这类题目我们还需要画图分析，如下所示：应该是C的4人加上B的6人。所以最少需要10个人",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统监理师","职业资格",0]