[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386326":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},386326,167,1,"单选题","某项目经理为某软件开发项目制作了如下双代号网络图（单位：天），该项目的总工期为（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","40",false,{"key":16,"text":17,"correct":18},"B","37",true,{"key":20,"text":21,"correct":14},"C","34",{"key":23,"text":24,"correct":14},"D","32","图中红色路线为关键路径，关键路径的总长度即为总工期，即37天；",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统监理师","职业资格",0]