[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386325":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},386325,167,1,"单选题","完成某信息系统集成项目中的一个最基本的工作单元A所需的时间，乐观的估计需7天，悲观的估计需19天，最可能的估计需13天，按照PERT方法进行估算，项目的工期应该为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","11",false,{"key":16,"text":17,"correct":14},"B","12",{"key":19,"text":20,"correct":21},"C","13",true,{"key":23,"text":24,"correct":14},"D","14","期望工期=（7+4*13+19）\u002F6=13",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统监理师","职业资格",0]