[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386321":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},386321,167,1,"单选题","以下关于成本控制说法错误的是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","在紧急情况下，应该先批准追加投资，其主要目的是为了保证项目的顺利进行",true,{"key":16,"text":17,"correct":18},"B","在项目实施过程中，必要时应对预算进行修正",false,{"key":20,"text":21,"correct":18},"C","应尽量保证项目的成本在原定的预算范围之内",{"key":23,"text":24,"correct":18},"D","对成本超支等情况，应及时进行分析并提出整改措施、总结教训","成本控制的目标和作用是：尽量使项目的执行不超出原定预算;必要时提出预算修正案;对实际发生的预算事件提出纠正措施，分析原因，总结教训。A选型错误，在需要追加投资时，第一步应该是提出变更申请，然后根据项目实际情况，对追加投资的原因进行分析，只有在得出此追加投资的合理性、必要性等有充分的理由时，才能追加投资。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统监理师","职业资格",0]