[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386312":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},386312,167,1,"单选题","变更在信息系统工程实际的建设过程中是经常发生的，做好变更控制可以更好地为质量控制、进度控制和成本控制服务。以下关于信息系统工程变更的说法，（ ）是不正确的。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目实施过程中，变更处理越早，损失越小",false,{"key":16,"text":17,"correct":14},"B","任何变更都要得到三方（建设单位、监理单位和承建单位）书面确认",{"key":19,"text":20,"correct":21},"C","只有承建单位和建设单位才能提出变更申请",true,{"key":23,"text":24,"correct":14},"D","建设单位由于机构重组等原因造成业务流程的变化，可能导致变更","变更的原则：三方都有权提出变更",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统监理师","职业资格",0]