[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386282":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},386282,167,1,"单选题","某软件工程项目各开发阶段工作量的比例如下表所示： 假设当前已处于编码阶段，3000行程序已完成了1200行，则可估算出该工程项目开发进度已完成的比例是（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","43%",false,{"key":16,"text":17,"correct":14},"B","49%",{"key":19,"text":20,"correct":21},"C","57%",true,{"key":23,"text":24,"correct":14},"D","63%","题目讲到：若当前处于编码阶段。说明需求分析,概要设计及详细设计都已完成, 共占0.49?（0.23+0.11+0.15）编码阶段3000行代码完成了1200行, 说明截至目前完成了编码部分的 1200\u002F3000 =0.4由于编码本身所占工作问题的比例是0.20 , 则截至目前完成的编码占总工程的 0.20*.0.4 =0.08加上前面各阶段所占 0.49+0.08= 0.57，所以完成的比例是57%",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统监理师","职业资格",0]