[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386278":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},386278,167,1,"单选题","在项目实施中间的某次周例会上，项目经理小王用下表向大家通报了目前的进度。根据这个表格，目前项目的进度是（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","提前于计划7%",false,{"key":16,"text":17,"correct":14},"B","落后于计划18%",{"key":19,"text":20,"correct":21},"C","落后于计划7%",true,{"key":23,"text":24,"correct":14},"D","落后于计划7.5%","当前，项目的挣值EV、PV及SPI值如下：EV = 20000*90%+50000*90%+30000*100% =93000PV = 20000+50000+30000 = 100000SPI = EV\u002FPV = 93000\u002F100000 = 93%1 - 93% = 7%，所以项目落后于计划 7%",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统监理师","职业资格",0]