[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386276":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},386276,167,1,"单选题","某信息化项目到2019年6月1日的成本执行数据如下表，根据下表数据当该项目为非典型偏差时，完工估算（EA C）为（ ）元，此项目目前（请作答此空）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","成本节约，进度落后",false,{"key":16,"text":17,"correct":14},"B","成本超支，进度超前",{"key":19,"text":20,"correct":21},"C","成本超支，进度落后",true,{"key":23,"text":24,"correct":14},"D","成本节约，进度超前","成本偏差CV=EV-AC=38410-47750=-9340；进度绩效指数SPI=EV\u002FPV=38410\u002F44100=0.87；因为成本偏差CV=EV-AC和进度偏差SV=EV-PV，都小于零，所以成本超支，进度落后。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统监理师","职业资格",0]