[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386270":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},386270,167,1,"单选题","某信息化工程建设过程中由于异常恶劣的气候条件，承建单位工期延误和费用增加，则停工期间承建单位可索赔（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工期、成本和利润",false,{"key":16,"text":17,"correct":14},"B","工期、成本，不能索赔利润",{"key":19,"text":20,"correct":21},"C","工期，不能索赔成本和利润",true,{"key":23,"text":24,"correct":14},"D","成本，不能索赔工期和利润","本题考查考生关于索赔管理的相关概念，如下表14项。标准施工合同中应给承包人补偿的条款",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统监理师","职业资格",0]