[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386261":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},386261,167,1,"单选题","在某工程网络计划中，工作E有两项紧后工作，这两项紧后工作的最早开始时间和最迟开始时间分别为21天和第25天，工作E的最早开始时间和最迟开始时间分别为第10天和第19天，如果工作E的持续时间为9天，则工作E的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总时差为9天",true,{"key":16,"text":17,"correct":18},"B","自由时差为1天",false,{"key":20,"text":21,"correct":18},"C","总时差为2天",{"key":23,"text":24,"correct":18},"D","自由时差为2天","总时差=LS-ES或LF-EF。所以本题中总时差为：最迟开始时间-最早开始时间=19-10=9。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统监理师","职业资格",0]