[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386244":3},{"question":4,"library":25},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":23},386244,167,1,"单选题","关于变更控制工作程序的描述，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","变更的初审→了解变化→变更分析→接受变更申请→确定变更方法→监控变更的实施→变更效果评估",false,{"key":16,"text":17,"correct":14},"B","了解变化→接受变更申请→确定变更方法→变更的初审→变更分析→监控变更的实施→变更效果评估",{"key":19,"text":20,"correct":14},"C","接受变更申请→了解变化→变更分析→确定变更方法→变更的初审→监控变更的实施→变更效果评估",{"key":22,"text":23,"correct":24},"D","了解变化→接受变更申请→变更的初审→变更分析→确定变更方法→监控变更的实施→变更效果评估",true,{"id":6,"name":26,"category":27,"favorite":28},"(中级) 信息系统监理师","职业资格",0]