[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386240":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},386240,167,1,"单选题","某信息系统建设项目，由于建设单位组织结构调整，造成项目进度延期，并导致监理合同约定的实施周期延长。针对上述情况，以下（ ）做法是妥当的。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","监理单位向承建单位索赔，挽回监理损失",false,{"key":16,"text":17,"correct":14},"B","承建单位要求追加实施费用",{"key":19,"text":20,"correct":14},"C","建设单位立即终止建设合同",{"key":22,"text":23,"correct":24},"D","监理单位要求追加监理费用",true,"项目索赔遵循索赔程序，在索赔证据确凿的条件下，可以根据合同向承建单位或建设单位提出索赔并得到损失的补偿。因而，合同管理是索赔管理的依据，依据合同条款的说明，项目索赔才能成立。由于建设单位的原因引起的进度拖延，监理单位可以要求建设单位提出追加监理费用。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统监理师","职业资格",0]