[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386235":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},386235,167,1,"单选题","承建单位提出验收申请后，监理单位必须首先审核验收计划和验收方案，主要审查内容是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","竣工结算文件",false,{"key":16,"text":17,"correct":18},"B","各方责任",true,{"key":20,"text":21,"correct":14},"C","授权证书",{"key":23,"text":24,"correct":14},"D","变更文档","承建单位提出验收申请后，监理单位必须首先审核验收计划和验收方案，主要审查内容是：1）验收目标;2）各方责任;3）验收内容;4）验收标准;5）验收方式。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统监理师","职业资格",0]