[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386227":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},386227,167,1,"单选题","完成某信息系统集成项目中的一个最基本的工作单元A所需的时间，乐观的估计需12天，悲观的估计需42天，最可能的估计需30天，按照PERT方法进行估算，项目的工期应该为（ ），在34天以后完成的概率大致为（请作答此空）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","8.9%",false,{"key":16,"text":17,"correct":18},"B","15.9%",true,{"key":20,"text":21,"correct":14},"C","22.2%",{"key":23,"text":24,"correct":14},"D","28.6%","标准差=（42-12）\u002F6=534天与29天之间为1个标准差（而非±1个标准差），29天到34天之间为±1个标准差，根据正态分布规律，故29天到34天之间完成的概率为68.26%，34天以后完成的概率=（1-68.26%）\u002F2=15.87%。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统监理师","职业资格",0]