[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386221":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},386221,167,1,"单选题","某系统集成项目包含了三个软件模块，现在估算项目成本时，项目经理考虑到其中的模块A技术成熟，已在以前类似项目中多次使用并成功支付，所有项目经理忽略了A的开发成本，只给A预留了5万元，以防意外发生。然后估算了B的成本为50万元，C成本为30万元，应急储备为10万元，三者集成成本为5万元，并预留了项目的10万元管理储备。如果你是项目组成员，该项目的成本基准是（ ）万元，项目预算是（ ）万元。项目开始执行后，当项目的进度绩效指数SPI为0.6时，项目实际花费为70万元，超出预算10万元，如果不加以纠偏，请根据当前项目进展，估算该项目的完工估算值（EA C）为（请作答此空）万元",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","64",false,{"key":16,"text":17,"correct":14},"B","134",{"key":19,"text":20,"correct":21},"C","194.4",true,{"key":23,"text":24,"correct":14},"D","124.4","项目实际花费AC为70万元，超出预算10万元，因此PV为60万元，SPI=EV\u002FPV=0.6,算得EV为36万元。项目未来不加以纠偏，属于典型偏差： EAC=ETC+AC=（BAC-EV）\u002Fcpi+AC=（100-36）*70\u002F36+70=194.4万元。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统监理师","职业资格",0]