[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386199":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},386199,167,1,"单选题","以下（ ）不属于成本估算工作所依赖的资料",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","未经评审的WBS",true,{"key":16,"text":17,"correct":18},"B","活动历时",false,{"key":20,"text":21,"correct":18},"C","资源需求",{"key":23,"text":24,"correct":18},"D","历史信息","WBS（工作分解结构），在分解时应该包含项目所有的活动，分解之后必须要经过评审才可以作为成本估算的依据。成本估算—依赖的资料（包括但不限于）工作分解结构WBS资源需求计划资源价格工作的延续时间历史信息会计表格",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统监理师","职业资格",0]