[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386195":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},386195,167,1,"单选题","成本估算的详细说明不包括（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工作估计范围描述",false,{"key":16,"text":17,"correct":14},"B","对于估计的基本说明",{"key":19,"text":20,"correct":14},"C","各种所作假设的说明",{"key":22,"text":23,"correct":24},"D","详细的里程碑计划",true,"成本估算的详细说明应该包括：工作估计范围描述，通常是依赖于WBS作为参考对于估计的基本说明，比如成本估算是如何实施的各种所作假设的说明指出估算结果的有效范围",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统监理师","职业资格",0]