[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386193":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},386193,167,1,"单选题","（ ）是项目成本管理的第一责任人。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总监",true,{"key":16,"text":17,"correct":18},"B","项目经理",false,{"key":20,"text":21,"correct":18},"C","财务主管",{"key":23,"text":24,"correct":18},"D","总经理","题目问的是项目成本管理的第一责任人；如果题目问公司财务统计的第一责任人，则有可能会选择C。本题CD为迷惑项，但对本知识点有深入理解的学员，应该很轻从做对。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统监理师","职业资格",0]