[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386151":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},386151,167,1,"单选题","索赔事件发生（ ），向监理工程师发出索赔意向通知",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","15天",false,{"key":16,"text":17,"correct":14},"B","20天",{"key":19,"text":20,"correct":21},"C","28天",true,{"key":23,"text":24,"correct":14},"D","30天","索赔事件发生28天内，向监理工程师发出索赔意向通知发出索赔意向通知后28天内，向监理工程师提出延长工期和（或）补偿经济损失的索赔报告及有关资料监理工程师在收到承建单位送交的索赔报告及有关资料后，于28天内给予答复，或要求承建单位进一步补充索赔理由和证据监理工程师在收到承建单位送交的索赔报告和有关资料后28天内未予答复或未对承建单位作进一步要求，视为该项索赔已经认可当该索赔事件持续进行时，承建单位应当阶段性向监理工程师发出索赔意向，在索赔事件终了28天内，向监理工程师送交索赔的有关资料和最终索赔报告。索赔答复程序与上述3、4规定相同，业主单位的反索赔的时限与上述规定相同监理工程师审查索赔报告",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统监理师","职业资格",0]