[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386147":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},386147,167,1,"单选题","暂停合同履行的前提条件不包括（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","由于承建单位的原因导致成本超支、进度滞后",true,{"key":16,"text":17,"correct":18},"B","单方违约导致合同确已无法履行，双方协议停止实施",false,{"key":20,"text":21,"correct":18},"C","法院要求停止实施",{"key":23,"text":24,"correct":18},"D","调解要求停止实施，且为双方接受","A选项错误，承建单位自身原因导致的成本超支、进度滞后，承建单位应对造成的后果负主要责任，在出现上述情况时，监理单位应责令承建单位“暂停施工”，对造成成本超支、进度滞后的原因进行充分分析并制定整改措施，而不是终止合同的履行。暂停履行合同的条件主要包括：单方违约导致合同确已无法履行，双方协议停止实施调解要求停止实施，且为双方接受仲裁机构要求停止实施法院要求停止实施",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统监理师","职业资格",0]