[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386144":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},386144,167,1,"单选题","关于违约金的计算方法，在每个合同文件中均有具体规定，一般按每延误一天赔偿一定的款额计算，累计赔偿额一般不正超过合同总额原（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","10%",true,{"key":16,"text":17,"correct":18},"B","15%",false,{"key":20,"text":21,"correct":18},"C","20%",{"key":23,"text":24,"correct":18},"D","30%","工期延误反索赔指工期延误属于承建单位责任时，业主单位对承建单位进行索赔，即由承建单位支付延期竣工违约金。业主单位在确定违约金的费率时，一般要考虑以下因素：业主单位盈利损失；工程拖期带来的附加监理费；由于本工程拖期竣工不能使用，造成的损失。违约金的计算方法，在每个合同文件中均有具体规定，一般按每延误一天赔偿一定的款额计算，累计赔偿额一般不正超过合同总额原10%。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统监理师","职业资格",0]