[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386135":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},386135,167,1,"单选题","如项目暂停是由于承建单位原因，承建单位在具备复工条件时，应填写（ ）报项目监理部审批，由总监理工程师签发审批意见；",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","整改计划",false,{"key":16,"text":17,"correct":14},"B","变更申请",{"key":19,"text":20,"correct":21},"C","复工申请",true,{"key":23,"text":24,"correct":14},"D","以上均不是","如项目暂停是由于承建单位原因，承建单位在具备复工条件时，应填写“复工报审表”报项目监理部审批，由总监理工程师签发审批意见；",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统监理师","职业资格",0]