[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386133":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},386133,167,1,"单选题","以下关于工期延期管理说法错误的是（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","非承建单位的责任使项目不能按原定工期开工",false,{"key":16,"text":17,"correct":14},"B","项目工作量变化和设计变更",{"key":19,"text":20,"correct":21},"C","非承建单位原因需要延期的，应经过监理单位同意工期相应顺延的其他情况",true,{"key":23,"text":24,"correct":14},"D","国家和地区有关部门正式发布的不可抗力事件","工程延期的管理：项目监理单位应对合同规定的下列原因造成的项目延期事件给予受理：非承建单位的责任使项目不能按原定工期开工；项目工作量变化和设计变更；非承建单位原因，造成一周內累计停水、停电（地区限电除外）、停气，而导致停工超过8小时；国家和地区有关部门正式发布的不可抗力事件；建设单位同意工期相应顺延的其他情况。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统监理师","职业资格",0]