[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386131":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},386131,167,1,"单选题","以下关于变更控制基本原则说法正确的是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","当变更申请提出时，应及时做出反应",true,{"key":16,"text":17,"correct":18},"B","变更的确认应得到监理的认可，认可后应严格按照变更流程来执行变更",false,{"key":20,"text":21,"correct":18},"C","承建单位以及建设单位都有权提出变更，监理单位主要负责对变更进行审核，而不是提出变更",{"key":23,"text":24,"correct":18},"D","变更申请提交之前应做好变更合理性、正确性的分析工作","认可变更都要经过三方确认，而B选项说只需要得到监理人可后便可执行变更的说法是错误的。C选项，监理不能提出变更也是错误的。D选项错误，变更流程的第一步是提交变更申请，随后由监理进行初审，并收集信息判断变更的必要性、合理性等。工程变更控制的基本原则：对变更申请快速响应任何变更都要得到三方确认明确界定项目变更的目标防止变更范围的扩大化三方都有权提出变更加强变更风险以及变更效果的评估及时公布变更信息选择冲击最小的方案",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统监理师","职业资格",0]