[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386129":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},386129,167,1,"单选题","关于变更控制的描述，不正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","变更申请单位向监理工程师提出变更要求，提交书面工程变更建议书",false,{"key":16,"text":17,"correct":14},"B","工程变更建议书应在预计可能变更的时间之前14天提出",{"key":19,"text":20,"correct":14},"C","变更的合理性应考虑是否会影响工作范围、成本、质量和时间",{"key":22,"text":23,"correct":24},"D","项目监理无权驳回变更申请",true,"项目监理根据项目实际情况，有权驳回变更申请",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统监理师","职业资格",0]