[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386122":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},386122,167,1,"单选题","项目描述表格的主要内容不包含（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目名称",false,{"key":16,"text":17,"correct":14},"B","项目目标",{"key":19,"text":20,"correct":21},"C","项目主要参与单位",true,{"key":23,"text":24,"correct":14},"D","工作规范","项目描述主要内容：项目名称项目目标交付物交付物完成准则工作描述工作规范所需资源估计重大里程碑项目主管审核意见",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统监理师","职业资格",0]